County Commission approves jail kitchen project
Cascade County Commissioners approved a $122,222 contract to Copper Creek Construction during their July 14 meeting for the kitchen grease interceptor project at the Cascade County Adult Detention Center.
County officials have determined the existing great interceptor in the jail kitchen is no longer adequate.
Over the last year, it has needed “significantly more frequent pumping, indicating it is operating beyond its intended capacity and design limitations; the existing steel interceptor is also rusted out and beginning to leak,” according to the staff report from the county public works department.
County discussing possible significant jail plumbing project, change to jail funding model
County officials have discussed the need for the project for years.
The county has worked with Big Sky Civil and Environmental on the project, and posted the bid package in May.
Bids were due by June 11.
County Commission approves jail booking remodel contract change
The county received three:
- Smith River Construction: $165,200
- Geranios Enterprises: $159,065.25
- Copper Creek: $122,222
BSCE and county staff reviewed the submittals and determined that Copper Creek submitted the lowest complete bid.
The project includes a new 2,500-gallon grease interceptor, influent and effluent piping, plus all necessary surface restoration.
According to the contract, the project will be substantially completed within 60 days of the contract start.