City Commission approves $2.5 million public works building remodel

City Commissioners approved a $2,543,315 contract during their Nov. 17 meeting to James Talcott Construction to remodel the public works administration building and addition.

The public works administration building at 1005 25th Ave. N.E. is more than 50 years old and has retained its original footprint, except for an addition for the environmental branch.

The project is being funded with water, sewer and stormwater funds.

City planning infrastructure fund with utility increase; potential new development position

A state safety audit found “serious electrical and overhead clearance issues,” and the facility lacks a dedicated meeting space for staff and office privacy for several management roles, according to the staff report.

The layout doesn’t align with current staff structure since it was originally designed as shop space and then retrofitted to accommodate public works administrative staff.

Commissioners approved a design contract to LPW in February for $210,970, of which $152,023.04 had been spent as of Nov. 5.

Construction will displace office employees to temporary job trailers on-site, requiring coordination to provide customer access.

City approves 27 percent utility increase, discussing how those new funds will be used [2025]

LPW completed the final architectural design, handled site investigations and assisted city staff with bid management. LPW will help city staff during construction with construction management services, performing special inspections as needed, submitting permit applications and assisting with plan review responses, according to the staff report.

As of Nov. 17, city engineering staff has spent 216 hours on the project.

City hires new public works director [2022]

The proposed improvements include:

The city received seven bids for the project ranging from $2,543,315 to $3,294,435.06, with James Talcott Construction submitting the low bid.

City considering budget during Aug. 4 meeting, includes tax increases

“Overall, this remodel will provide an improved first impression to customers, contractors, employees and other visitors to the facility. This is the first major facility work since the 1970s. This remodel and addition will support public works in its role of providing for the infrastructure needs of a growing Great Falls,” according to the staff report.

City staff visited officials in Bozeman and Belgrade earlier this fall to discuss the impact of growth and a lesson learned highlighted by Bozeman officials was “severe morale and retention issues,” due primarily to salary not commensurate with the local cost of living and a lack of sufficient quality work spaces for employees, according to the staff report.