Site icon The Electric

City completes 4th Avenue North street reconstruction

City Commissioners approved final payment during  their Sept. 16 meeting for the 4th Avenue North street reconstruction project.

That was $96,950.09 to United Materials and $979.29 to the State Miscellaneous Tax Fund.

The project included installing base course, asphalt pavement, curb and gutter, storm drain inlets and ADA compliant handicap ramps along 4th Avenue North from 9th to 14th Street North.

The project was needed, according to staff, due to aging infrastructure, such as:

The project started and was completed ahead of schedule.

One tree was removed at the southeast corner of 4th Avenue North and 10th Street North for installation of ADA-compliant ramps. The tree was replaced with two trees planted nearby.

City considering street assessment increase in effort to improve overall street network; discuss development impact

Woith Engineering completed design phase engineering and city staff provided construction phase engineering and project inspection.

The final project cost was $1,958,587.59, which was is $105,062.41 less than the original contract award of $2,063,650, largely due to the minimal use of sub-base material, imported trench backfill and sod restoration.

Substantial completion of the project was June 26 at which point the two-year warranty period began.

The project was selected under public works’ capital improvement plan and 86 percent was funded by the street fund and the remainder by the storm drain fund.

Exit mobile version