Work is underway to repair the failing pond wall in Gibson Park.
The city awarded the contract to Ivers Construction and Concrete in September for $53,394.
The project involves 120 feet of 8-feet by 12-feet reinforced sidewalk that will tie into the pond wall to keep it from failing further, according to Park and Recreation.
City approves $18.34 million contract for indoor pool construction
The pond wall repair was first requested in 2010, according to the city’s capital improvement plan.
In that document, it states, “wall is falling in on back side of Gibson Pond on the northeast side. Repairs would consist of draining the pond or isolating the failing area. The wall and trail would both need to be repaired. Cementing the entire pond is also an option, but it would be at a much larger expense.”
City reinvesting savings from park district projects into other Park and Rec improvements
The project was estimated at $165,000 in that document.
The pond wall failure has been a concern as it could constitute a public safety hazard, according to city officials for years, and in the capital improvement plan, officials said the separation was increasing with a high chance of failure.